| What should be done to ensure dredging does not harm marine productivity? | consultation with Expert Institute such as Central Water and Power Research Station (CWPRS) Pune or any other Institute | PD-11011/2/92-NMPT dated 7th May, 1993 seeking environmental clearance for the above mentioned proposal. 2% The proposal has been examined and environmental clearance is hereby accorded subject to the following conditions:- (i) Dredging operations should be undertaken in consultation with Expert Institute such as Central Water and Power Research Station (CWPRS) Pune or any other Institute to ensure that dredging operaticns do not cause any adverse impact on surface and ground water and marine productivity in the vicinity. During dredging, construction and maintenance stages, the water quality parameters at the bottom level should be inspected and periodic records be maintained. Tests should be carried measure water quality parameters viz. turbidity, dissolved oxygen, ammonical nitrogen and other nutrients which must be maintained within the prescribed standards. | 272 | relationship | 0.970 | 2% The proposal has been examined and environmental clearance is hereby accorded subject to the following conditions:- (i) Dredging operations should be undertaken in consultation with Expert Institute such as Central Water and Power Research Station (CWPRS) Pune or any other Institute to ensure that dredging operaticns do not cause any adverse impact on surface and ground water and marine productivity in the vicinity. | 1 | page=1,ocr=1 | 0.700 | valid |
| What should be ensured during dredging operations to avoid adverse environmental impacts? | dredging operaticns do not cause any adverse impact on surface and ground water and marine productivity in the vicinity. | PD-11011/2/92-NMPT dated 7th May, 1993 seeking environmental clearance for the above mentioned proposal. 2% The proposal has been examined and environmental clearance is hereby accorded subject to the following conditions:- (i) Dredging operations should be undertaken in consultation with Expert Institute such as Central Water and Power Research Station (CWPRS) Pune or any other Institute to ensure that dredging operaticns do not cause any adverse impact on surface and ground water and marine productivity in the vicinity. During dredging, construction and maintenance stages, the water quality parameters at the bottom level should be inspected and periodic records be maintained. Tests should be carried measure water quality parameters viz. turbidity, dissolved oxygen, ammonical nitrogen and other nutrients which must be maintained within the prescribed standards. | 407 | relationship | 0.970 | 2% The proposal has been examined and environmental clearance is hereby accorded subject to the following conditions:- (i) Dredging operations should be undertaken in consultation with Expert Institute such as Central Water and Power Research Station (CWPRS) Pune or any other Institute to ensure that dredging operaticns do not cause any adverse impact on surface and ground water and marine productivity in the vicinity. During dredging, construction and maintenance stages, the water quality parameters at the bottom level should be inspected and periodic records be maintained. |
| What must be ensured in case of deviations or alterations in the project proposal? | these stipulations may be modified and or new ones imposed for ensuring protection. | Adequate financial provision must be made for tion of the above stipulations, 3 Se In case of any deviation/alternations in the project proposal from those submitted to this Ministry for clearance, these stipulations may be modified and or new ones imposed for ensuring protection. | 198 | summary | 0.970 | Adequate financial provision must be made for tion of the above stipulations, 3 Se In case of any deviation/alternations in the project proposal from those submitted to this Ministry for clearance, these stipulations may be modified and or new ones imposed for ensuring protection. | 2 | page=2,ocr=1 | 0.700 | valid |
| What is the purpose of the development project mentioned in the memorandum? | Development of port facilities for handling of crude and POL products at Mangalore Port. | PARYAVARAN, DELHI te : Telephone 4361316 W-66185 DOE IN 4260678 Te ef GOVERNMENT OF MINISTRY OF ENVIRONMENT & FORESTS au \ eh > PARYAVARAN BHAWAN, C.G.0. COMPLEX wer aiet rie, ag ROAD, NEW DELHE-110003 29th October, 1993. OFFICE MEMORANDUM Development of port facilities for handling of crude and POL products at Mangalore Port. Reference is invited to New Mangalore Port Trust's letter No.3/11/EMP/92-IS dated 31.10.1992 and Ministry of Surface Transport's letter No. | 240 | summary | 0.970 | OFFICE MEMORANDUM Development of port facilities for handling of crude and POL products at Mangalore Port. Reference is invited to New Mangalore Port Trust's letter No.3/11/EMP/92-IS dated 31.10.1992 and Ministry of Surface Transport's letter No. | 1 | page=1,ocr=1 | 0.700 | valid |
| What water quality parameters must be measured during dredging? | turbidity, dissolved oxygen, ammonical nitrogen and other nutrients | PD-11011/2/92-NMPT dated 7th May, 1993 seeking environmental clearance for the above mentioned proposal. 2% The proposal has been examined and environmental clearance is hereby accorded subject to the following conditions:- (i) Dredging operations should be undertaken in consultation with Expert Institute such as Central Water and Power Research Station (CWPRS) Pune or any other Institute to ensure that dredging operaticns do not cause any adverse impact on surface and ground water and marine productivity in the vicinity. During dredging, construction and maintenance stages, the water quality parameters at the bottom level should be inspected and periodic records be maintained. Tests should be carried measure water quality parameters viz. turbidity, dissolved oxygen, ammonical nitrogen and other nutrients which must be maintained within the prescribed standards. | 749 | list | 0.820 | Tests should be carried measure water quality parameters viz. turbidity, dissolved oxygen, ammonical nitrogen and other nutrients which must be maintained within the prescribed standards. | 1 | page=1,ocr=1 |
| What potential emergencies should be addressed in the Disaster Management Plan? | oil/chemical spills, fire/explosion, terrorist attack, flood | (iv) In addition to the Disaster Management Plan prepared, the project authorities should consider worst case scenario with respect to specific cases like oil/chemical spills, fire/explosion, terrorist attack, flood etc..spelling out definite adequate measures to be taken to prevent and contain such | Gisasters. A report on this must be forwarded to Ministry within six months from the date of issue of environmental clearance, (v) To prevent discharge of sewage, bilge wastes and other liquid wastes into the marine environment, adequate system for collection, treatment and disposal of liquic wastes including shoreline interceptor for receiving liquid wastes from all shoreline installations and Special hose connection for ships to allow for discharg of sewage must be provided. (vi) Green belt development programme as proposed must be Carried out. | 155 | list | 0.820 | (iv) In addition to the Disaster Management Plan prepared, the project authorities should consider worst case scenario with respect to specific cases like oil/chemical spills, fire/explosion, terrorist attack, flood etc..spelling out definite adequate measures to be taken to prevent and contain such | Gisasters. |
| Under which acts will the stipulations be enforced? | the Water (Prevention & Control of Pollution) Act, 1974. The Air (Prevention & Control of Pollution) Act, 1981, and the Environment (Protection) Act, 1986. | 6. These stipulations will be enforced among others under the Water (Prevention & Control of Pollution) Act, 1974. The Air (Prevention & Control of Pollution) Act, 1981, and the Environment (Protection) Act, 1986. Joint Director (Scientific) To The Secretary, Ministry of Surface Transport, Parivahan Bhavan, Parliament Street, NEW DELHI - 110001, Copy to:- (0 Chairman, New Mangalore Port Trust, Panambur, Mangalore-575 010, Ze Chairman, Central Pollution Control Board, Parivesh Bhavan, CBD-cum-Office Complex, East Arjun Nagar, Shahdra, Delhi-32. Chief Conservator of Forests, Regional Office (Southern zone), Ministry of Environment & Forests, No.463, lst Main, IIIrd Stage, IIIrd Block, BasaveshwaraNnagar, Bangalore-560 079, 4, Chairman, State Pollution Control Board (Karnataka), No. 25, 6th, 7th & 8th Floor, Public utility Building, M.G. | 58 | list | 0.820 | These stipulations will be enforced among others under the Water (Prevention & Control of Pollution) Act, 1974. The Air (Prevention & Control of Pollution) Act, 1981, and the Environment (Protection) Act, 1986. Joint Director (Scientific) To The Secretary, Ministry of Surface Transport, Parivahan Bhavan, Parliament Street, NEW DELHI - 110001, Copy to:- (0 Chairman, New Mangalore Port Trust, Panambur, Mangalore-575 010, Ze Chairman, Central Pollution Control Board, Parivesh Bhavan, CBD-cum-Office Complex, East Arjun Nagar, Shahdra, Delhi-32. |
| What parameters must be maintained within prescribed standards during dredging operations? | turbidity, dissolved oxygen, ammonical nitrogen and other nutrients | PD-11011/2/92-NMPT dated 7th May, 1993 seeking environmental clearance for the above mentioned proposal. 2% The proposal has been examined and environmental clearance is hereby accorded subject to the following conditions:- (i) Dredging operations should be undertaken in consultation with Expert Institute such as Central Water and Power Research Station (CWPRS) Pune or any other Institute to ensure that dredging operaticns do not cause any adverse impact on surface and ground water and marine productivity in the vicinity. During dredging, construction and maintenance stages, the water quality parameters at the bottom level should be inspected and periodic records be maintained. Tests should be carried measure water quality parameters viz. turbidity, dissolved oxygen, ammonical nitrogen and other nutrients which must be maintained within the prescribed standards. | 749 | list | 0.820 | Tests should be carried measure water quality parameters viz. turbidity, dissolved oxygen, ammonical nitrogen and other nutrients which must be maintained within the prescribed standards. | 1 | page=1,ocr=1 |
| What scenarios should the Disaster Management Plan consider? | oil/chemical spills, fire/explosion, terrorist attack, flood | (iv) In addition to the Disaster Management Plan prepared, the project authorities should consider worst case scenario with respect to specific cases like oil/chemical spills, fire/explosion, terrorist attack, flood etc..spelling out definite adequate measures to be taken to prevent and contain such | Gisasters. A report on this must be forwarded to Ministry within six months from the date of issue of environmental clearance, (v) To prevent discharge of sewage, bilge wastes and other liquid wastes into the marine environment, adequate system for collection, treatment and disposal of liquic wastes including shoreline interceptor for receiving liquid wastes from all shoreline installations and Special hose connection for ships to allow for discharg of sewage must be provided. (vi) Green belt development programme as proposed must be Carried out. | 155 | list | 0.820 | (iv) In addition to the Disaster Management Plan prepared, the project authorities should consider worst case scenario with respect to specific cases like oil/chemical spills, fire/explosion, terrorist attack, flood etc..spelling out definite adequate measures to be taken to prevent and contain such | Gisasters. |
| What measures should be adopted to control noise levels in the port area? | providing muffl to muffle the sound from engines motors etc., rubber paddings while installing machines, to workers working in the noisy environment | suitable species of trees must also be planted along the existing roads in the port area, open vacant spaces and along the shoreline. (vii) Adequate noise control measures such as providing muffl to muffle the sound from engines motors etc., rubber paddings while installing machines, to workers working in the noisy environment to contain the noise within prescribed standards must be adopted. (viii) The quality of treated effluents, solid wastes, emissicns and noise levels etc., must conform to the Standards laid down by the competent authorities including Central/State Pollution Control Board and under the Environment (Protection) Act, 1986, whichever! are more stringent. | In the New Mangalore Port Trust, sufficient Capability (environment cell) should be created to monitor and implement the programme related to pollution control and environmental conservation. 4. | 180 | list | 0.820 | (vii) Adequate noise control measures such as providing muffl to muffle the sound from engines motors etc., rubber paddings while installing machines, to workers working in the noisy environment to contain the noise within prescribed standards must be adopted. |